Ordered-Length Cable Procurement Schedule
Method & Assumptions
Cables are grouped by conductor specification (type + size + material). A field-trim tolerance (default 3%) is added to each cable's routed length per IEEE 1185 §6.4 to account for connector strain relief and termination offcuts.
The required cut lengths are assigned to standard reel sizes using a greedy first-fit-decreasing bin-packing algorithm. Cuts are placed on the first reel with sufficient remaining capacity; a new reel is opened only when no existing reel can accommodate the cut. A 5% residual threshold prevents reels from being used when only a tiny sliver remains.
References: IEEE Std 1185 §6.4, ICEA S-93-639, NEC Article 310.
See also: Pull Cards, Spool Sheets, Optimal Route.
No routing results found in the current session. Please run cable routing on the Optimal Route page first, then return here to generate the procurement schedule.
Summary
Line Items
One row per cable specification. Expand the Cuts column to see individual cable assignments.
| Spec | Type | Size | Conductors | Cut Count | Total Req. (ft) | Reel Size | # Reels | Total Ordered (ft) | Waste (ft) | Waste (%) | Cuts |
|---|