Project Cost Estimator
Method & Pricing Basis
Material costs are estimated from unit prices ($/ft for cable, tray, conduit) multiplied by quantities from the project schedules. Cable lengths come from routing results if available, otherwise from the cable schedule.
Labor costs use built-in conceptual productivity allowances:
- Cable pull: 150 ft/hr → $75/hr = $0.50/ft installed
- Tray installation: 30 ft/hr → $90/hr = $3.00/ft installed
- Conduit installation: 25 ft/hr → $85/hr = $3.40/ft installed
Default unit prices are built-in 2024 USD conceptual allowances, not a licensed cost-book extract. Import a current supplier, internal, or licensed cost source for issued estimates.
This estimate does not include: engineering fees, permits, switchgear, transformers, or conduit fittings beyond a default unit cost per fitting.
Estimate Basis & Escalation
Normalize a pricing book to the project region and estimate date. Index values are stored with the estimate so a later reviewer can reproduce the adjustment without a live data connection.
Regional Labor Basis
Regional factor = local wage ÷ national wage. The national reference is the BLS OEWS May 2024 median annual electrician wage ($62,350 ÷ 2,080 hr). Enter the comparable local OEWS value; this factor scales the loaded contractor labor rates, not the wage itself.
Material Escalation
Labor Escalation
Price Overrides (optional)
Added to the grand total as a percentage allowance.
Click Generate Estimate to compute project costs from your schedules.