Method & Pricing Basis

When successful route results are available, material costs use a signed route-scoped quantity ledger: cable length includes physical-run multiplicity, while shared installed trays and conduits are counted once by schedule identity. Without routes, schedule quantities remain available as a conceptual fallback.

Labor costs use built-in conceptual productivity allowances for linear electrical work:

  • Cable pull: 150 ft/hr → $75/hr = $0.50/ft installed
  • Tray installation: 30 ft/hr → $90/hr = $3.00/ft installed
  • Conduit installation: 25 ft/hr → $85/hr = $3.40/ft installed

Route-ledger tray support counts are priced as separate assemblies. Tray fitting labor requires imported fitting productivity. Routed ductbanks reuse the Ductbank Route BOM for conduit, accessories, structures, fittings, excavation, bedding, concrete, and backfill; every mixed-unit BOM line requires imported material price and labor-hours-per-unit evidence.

Default unit prices are built-in 2024 USD conceptual allowances, not a licensed cost-book extract. Import a current supplier, internal, or licensed cost source to complete the governed-price checks. Output remains classified Screening only and is not a bid or issued estimate.

This estimate does not include: engineering fees, permits, switchgear, transformers, taxes, freight, contractor markup, dewatering, rock excavation, or unmodeled field conditions.

Estimate Basis & Escalation

Normalize a pricing book to the project region and estimate date. Index values are stored with the estimate so a later reviewer can reproduce the adjustment without a live data connection.

Regional Labor Basis

Regional factor = local wage ÷ national wage. The national reference is the BLS OEWS May 2024 median annual electrician wage ($62,350 ÷ 2,080 hr). Enter the comparable local OEWS value; this factor scales the loaded contractor labor rates, not the wage itself.

Material Escalation

Labor Escalation

Price Overrides (optional)

Added to the grand total as a percentage allowance.

Click Generate Estimate to compute project costs from your schedules.